Last updated:
9 August, 2023
Proposer
Steve Mulinganie
Modification type
Urgent
Status:
Rejected
29/05/2020
Impact:
Low impact: Suppliers
Medium impact: CDSP, GB Gas Transporters, Independent Gas Transporters, National Gas Transmission, National Transmission System
High impact: Consumers, Shippers
To enable consumers to have their site SOQ updated to more accurately reflect their network use during the COVID-19 pandemic and to authorise the CDSP to temporarily accept Shipper User SOQ update requests outside of the normal period.
Timeline
Panel Assessment
Yes
07/05/2020
Status
Ofgem Decision on Urgency
Ofgem Decision on Urgency
Workgroup Report Due
Unset
Consultation
Completed
11/05/2020
13/05/2020
Consultation - Final Modification Report
Yes
18/05/2020
Status
Final Modification Report available for Panel
Panel Decision
Yes
22/05/2020
Status
Ofgem Decision
Implementation
Unset