To review the market principles and existing commercial framework in order to assess their compatibility with blending hydrogen into the networks and explore the required amendments where necessary. Ensuring the amended regime is simple and easy to implement whilst also remaining adaptable and consistent with relevant obligations. KPMG will be providing project management support for the project.
Schedule of topics to be discussed at future Workgroup meetings:
18th March (full day)
- Capacity allocation & connections (first 2 hours)
- Nominations, settlement & balancing
2nd April (full day) Shrinkage, network charging & other issues
7th April (GQ workgroup)
- Gas quality & system ops
30th April (full-day) NTS & GDN Interface and Any other outstanding issues from previous sessions
4th June - LDZ level blending (Tentative 10-4pm)
10th June - NTS level blending (Tentative 10-4pm)
10th July - all remaining issues (Tentative 10-4pm)